Contents*Click here to view the amendment codes key.:
71; SPONSOR CONTROLLED BOARD; SCHEDULE A - NEW; REVISED FLOOR PLANS; SPONSOR FINANCIAL DISCLOSURE ITEMS; 99 - CERT. OF OCCUPANCY ISSUED FOR THE BUILDING; THE PCO ESCROW ACCOUNT HAS BEEN CLOSED AND ALL FUNDS HAVE BEEN RELEASED TO SPONSOR; RENAME UNIT TH-A TO "THIRD FLOOR"; STATUS OF UNSOLD UNITS; CHANGE IN SPONSOR CONTROL; (12)
Contents*Click here to view the amendment codes key.:
20 - EFFECTIVE BY 1 UNIT = 20% IN CONTRACT, EFFECTIVE BY AMENDMENT. 71, ENGINEER'S - ARCHITECT'S CERTIFICATION, REVISED DESCRIPTION OF PROPERTY, REVISED FLOOR PLANS. (6)
Contents*Click here to view the amendment codes key.:
11 - CHANGE IN PRICE $14,200,000, NEW TOTAL OFFERING PRICE $141,395,000, FORM CD-11 ATT'ED, SCHEDULE A - NEW, REVISED FLOOR PLANS, ENGINEER'S - ARCHITECT'S CERTIFICATION, COMBINED UNITS, ESCROW TRUST FUND REVISIONS (2012), 99 - 339-I CERTIFICATION. (6)